Park Lake City
Construction progress for December 2023

08.11.2023

Go back

Park Lake City by DIM is actively under construction.

We share the latest construction report for December:

VITA quarter, second line

House No. 2.1:

  • Electrical wiring – 90%

  • Facade lighting installation – 99%

  • Heating distribution system – 85%

  • Device K1, K2, B1 – 60%

  • External network setup – 95%

  • Ceiling installation of the GC – 75%

  • Installation of entrance doors – 75%

  • Installation of raised floor on the first floor – 2%

  • Installation of porcelain tiles on the floor – 15%

  • Brickwork of the house – 100%

House No. 2.4:

  • Installation of window structures – 100%

  • Roofing – 62%

House No. 2.5:

  • Window installation – 92%

House No. 2.7:

  • Installation of geothermal wells for heat pumps – 75%

  • Installation of the foundation slab for the building – 100%