Construction progress for September 2023

29.09.2023

Go back

Park Lake City by DIM is actively under construction.

We share the latest construction report for September:

VITA Quarter, first phase

House No. 1.5:

  • Basement insulation – 100%

  • Window installation – 75%

  • Waterproofing of balconies – 80%

  • Porch installation – 50%

VITA quarter, second line

House No. 2.1:

  • Arrangement of front gardens – 90%

House No. 2.3:

  • Window installation – 85%

House No. 2.4:

  • Facade installation – 28%

  • Roof installation – 15%

House No. 2.5:

  • Window installation – 90%

House No. 2.7:

  • Soil replacement for the building foundation – 90%

AQUA Quarter, first phase

House No. 1.1:

  • Bricklaying – 45%

House No. 1.3:

  • Installation of a monolithic building frame – 60%

Local treatment plants:

  • Foundation construction – 80%