Construction progress for February 2023
22.03.2023
The unique suburban business-class complex PARK LAKE CITY from the DIM company is actively being built. We are making the project even more comfortable, planting even more trees and plants, equipping new recreation areas and lighting. Facade and masonry work is being carried out in the buildings.
We report in detail on the work completed in February:
VITA Quarter, first phase
House No. 1:
Covered parking – 50%
Landscaping works – 95%
House No. 3:
Installing a treadmill near the house – 95%
Installation of benches – 100%
Backfilling of porches with pebbles – 10%
Plastering apartments with White box – 100%
House No. 4:
Plastering apartments with White box – 100%
Showroom setup – 20%
House No. 5:
Brickwork throughout the house – 98%
Roof installation – 98%
Clean water tank:
SS – 15%
Reservoir hilling, preparation of landscaping for final coating – 98%
Ventilation system – 60%
Beach area arrangement – 100%
VITA Quarter, second phase
House No. 2.1:
Electricity distribution – 80%
Facade installation – 85%
Facade lighting installation – 95%
Installation of wiring for a video surveillance system – 100%
Ebb and flow arrangement – 99%
Installation of balcony railing posts – 100%
Basement waterproofing – 100%
Soil replacement for terraces and entrance groups – 95%
Roof installation – 90%
House No. 2.2:
Facade installation – 80%
Facade lighting installation – 95%
Installation of wiring for a video surveillance system – 100%
Ebb and flow arrangement – 99%
Installation of balcony railing posts – 100%
Basement waterproofing – 25%
Soil replacement for terraces and entrance groups – 97%
Roof installation – 90%
House No. 2.3:
Roofing work is underway – 90% complete
House No. 2.4:
Masonry installation – 97% (the rest after the raised floor slab)
House No. 2.5:
Masonry installation – 98% (the rest after the raised floor slab)
AUQA Quarter 2
Parking:
Soil replacement – 99%
TERRA Quarter 1
House No. 2:
Masonry installation – 6%