Park Lake City by DIM is under construction.

We share detailed construction news for August:

VITA Quarter, first phase

House No. 1.5:

  • Basement insulation – 50%

  • Window installation – 65%

  • Waterproofing of the 1st floor – 100%

  • Waterproofing of balconies – 70%

VITA quarter, second line

House No. 2.1:

  • Backfilling of the power floor with sand – 100%

  • Floor insulation – 100%

  • Arrangement of front gardens – 15%

House No. 2.2:

  • Porch installation – 100%

House No. 2.3:

  • Window installation – 48%

  • Basement insulation – 100%

House No. 2.4:

  • Facade installation – 21%

House No. 2.5:

  • Window installation – 62%

House No. 2.6:

  • Monolith execution – 100%

House No. 2.7:

  • Soil replacement for the building foundation – 15%

AQUA Quarter, first phase

House No. 1.1:

  • Installation of monolithic stairs – 100%

House No. 1.3:

  • Installation of the building foundation slab – 100%

  • Installation of a monolithic building frame – 3%

Local treatment plants:

  • Foundation construction – 70%