Construction progress for July 2023
20.07.2023
PARK LAKE CITY by DIM is under construction. We share detailed construction news for July:
VITA Quarter, first phase
House No. 1.5:
Window installation – 60%
Installation of cables according to the permanent power supply scheme – 100%
Exterior lighting of the house – 50%
Arrangement of the beach area:
Planting perennials – 100%
Arrangement of landscaping of protective curbs – 30%
VITA quarter, second line
House No. 2.1:
Installation of electricity distribution – 84%
Arrangement of the house contour for landscaping – 80%
Installation of brick partitions on porches (demarcation of apartments) – 100%
Retaining wall installation – 100%
Installation of plates for air conditioners – 100%
Sand filling of the first floor – 100%
House No. 2.2:
Installation of ventilation grilles on the roof – 30%
Installation of plates for air conditioners – 100%
House No. 2.3:
Installation of geothermal wells for heat pumps – 100%
Installation of aluminum windows – 20%
House No. 2.4:
Facade installation – 20%
House No. 2.5:
Window installation – 45%
House No. 2.6:
Monolith installation – 98%