PARK LAKE CITY by DIM is under construction. We share detailed construction news for July:

VITA Quarter, first phase

House No. 1.5:

  • Window installation – 60%

  • Installation of cables according to the permanent power supply scheme – 100%

  • Exterior lighting of the house – 50%

Arrangement of the beach area:

  • Planting perennials – 100%

  • Arrangement of landscaping of protective curbs – 30%

VITA quarter, second line

House No. 2.1:

  • Installation of electricity distribution – 84%

  • Arrangement of the house contour for landscaping – 80%

  • Installation of brick partitions on porches (demarcation of apartments) – 100%

  • Retaining wall installation – 100%

  • Installation of plates for air conditioners – 100%

  • Sand filling of the first floor – 100%

House No. 2.2:

  • Installation of ventilation grilles on the roof – 30%

  • Installation of plates for air conditioners – 100%

House No. 2.3:

  • Installation of geothermal wells for heat pumps – 100%

  • Installation of aluminum windows – 20%

House No. 2.4:

  • Facade installation – 20%

House No. 2.5:

  • Window installation – 45%

House No. 2.6:

  • Monolith installation – 98%