Park Lake City
Construction progress for March 2023

29.03.2023

Go back

PARK LAKE CITY – a suburban eco-complex of business class from the DIM company is under construction. Work is underway on the construction of houses, landscaping, planting trees, and arranging recreation areas. With the arrival of spring, the grandeur of nature and the architectural features of the project captivate and leave no one indifferent.

We are sharing a fresh photo report from the construction site for March:

VITA Quarter, first phase

Playground:

  • Applying the finishing coat – 95%

  • Lighting installation – 10%

  • Automatic watering device – 95%

  • Landscaping work completed – 100%

House No. 1:

  • Installation of benches – 100%

  • Covered parking – 55%

  • Landscaping work completed – 97%

House No. 2:

  • Refurbishment of the recreation area, fireplace

  • Installing benches

House No. 3:

  • Automatic watering device – 99%

  • Installing a treadmill near the house – 97%

  • Tree planting – 95%

  • Installation of benches – 100%

House No. 4:

  • Automatic watering device – 99%

  • Preparation of vertical planning for tree planting – 100%

  • Tree planting – 95%

House No. 5:

  • Brickwork throughout the house – 97%

  • Pulling of EO cables according to a permanent scheme (input) – 80%

  • Roof installation – 99%

Clean water tank:

  • SS – 18%

  • Reservoir hilling, preparation of landscaping for final coating – 99%

  • Connection of EO under a permanent scheme – 100%

  • Ventilation system – 65%

  • Installation of outdoor lighting poles – 100%

VITA quarter, second line

House No. 2.1:

  • Electricity distribution – 82%

  • Facade arrangement – 87%

  • Installation of screed on balconies – 100%

  • Facade lighting installation – 96%

  • Soil replacement under the terrace and entrance groups – 96%

  • Roof installation – 92%

  • Installation of porcelain tiles on the facade – 60%

House No. 2.2:

  • Facade arrangement – 82%

  • Facade lighting installation – 96%

  • Installation of screed on balconies – 100%

  • Ebb and flow arrangement – 100%

  • Basement waterproofing – 28%

  • Soil replacement under the terrace and entrance groups – 98%

  • Roof installation – 93%

  • Installation of porcelain tiles on the facade – 60%

House No. 2.3:

  • Roofing work is underway – 92%

House No. 2.4:

  • Masonry installation – 97% (the rest after the raised floor slab)

House No. 2.5:

  • Masonry installation – 99% (the rest after the raised floor slab)

TERRA Quarter 1

House No. 2:

  • Masonry installation – 8%

  • Automatic watering camera setup – 100%