Park Lake City
Construction progress for May 2023

09.05.2023

Go back

PARK LAKE CITY – a business-class suburban eco-complex from DIM is actively being built. New houses are growing, new trees are being planted.

We share detailed construction news for May:

VITA Quarter, first phase

Playground:

  • Application of the finishing coating – 97%

  • Arrangement of open parking – 100%

  • Planting thuja for a "green wall" - 100%

House No. 1.5:

  • Basement waterproofing – 100%

  • Preparatory work for elevator installation – 100%

  • Window installation – 5%

  • Soil replacement for terraces, entrance groups and parking – 90%

Clean water tank:

  • Ventilation system – 100%

VITA quarter, second line

House No. 2.1:

  • Facade installation – 89%

  • Installation of ventilation grilles on the roof – 100%

  • Porch installation – 10%

House No. 2.2:

  • Installation of ventilation grilles on the roof – 100%

House No. 2.3:

  • Soil replacement – 100%

  • Installation of geothermal wells for heat pumps – 30%

  • Elevator installation – 95%

House No. 2.4

  • Installation of mortgages for freon pipes – 100%

  • Installation of K14 embedded systems – 100%

  • Basement waterproofing – 100%

  • Basement insulation – 100%

  • Facade installation – 15%

  • Roof installation – 5%

House No. 2.5

  • Basement waterproofing – 50%

  • Installation of mortgages for freon pipes – 100%

House No. 2.6:

  • Monolith installation – 50%