Construction progress for April 2024

24.04.2024

Go back

Park Lake City by DIM is under construction.

We share a fresh construction report for April:

VITA quarter, first line

House No. 1.3:

  • installation of front garden fencing - 20%

House No. 1.5:

  • installation of windows - 100%
  • installation of a running track near the house - 50%

VITA quarter, second line

House No. 2.1:

  • installation of porcelain tiles on the facade - 100%
  • arrangement of heating distribution - 100%
  • landscaping - 42%
  • installation of false floors on the first floor - 95%
  • installation of porcelain tiles on the floor - 95%

House No. 2.2:

  • filling with sand under the power plate - 90%

House No. 2.3:

  • installation of geothermal wells for heat pumps - 100%

House No. 2.5:

  • installation of windows - 100%

House No. 2.6:

  • arrangement of masonry - 90%

House No. 2.7:

  • arrangement of construction materials - 100%

House No. 2.8:

  • arrangement of piles under the building - 95%

House No. 2.9:

  • arrangement of technical underground - 90%
  • arrangement of piles under the building - 100%

AQUA quarter, first line

House No. 1.1:

  • installation of ventilation units - 90%

House No. 1.3:

  • arrangement of masonry - 25%