Park Lake City
Construction progress for October 2024

11.11.2024

Go back

We share the latest construction report for October:

VITA Quarter, first stage

House No. 1.5:

  • facade installation – 40%
  • auto-watering installation – 70%
  • external networks installation completed – 100%
  • territory landscaping – 25%

VITA Quarter, second stage

House No. 2.1:

  • SKD installation – 96%
  • furniture structures installation completed in the lobby – 100%
  • furniture structures installation in the MZK – 25%
  • front garden fencing installation – 52%

House No. 2.3:

  • facade installation – 45%
  • K13 installation – 90%

House No. 2.6:

  • window installation - 13%

House No. 2.7:

  • foundation waterproofing – 50%

House No. 2.8:

  • building monolith installation – 30%

Building No. 2.9:

  • installation of the monolith of the building completed – 100%

AQUA Quarter, first stage

Local wastewater treatment plants:

  • installation of equipment – ​​25%