Construction progress for October 2024
11.11.2024
Go back
We share the latest construction report for October:
VITA Quarter, first stage
House No. 1.5:
- facade installation – 40%
- auto-watering installation – 70%
- external networks installation completed – 100%
- territory landscaping – 25%
VITA Quarter, second stage
House No. 2.1:
- SKD installation – 96%
- furniture structures installation completed in the lobby – 100%
- furniture structures installation in the MZK – 25%
- front garden fencing installation – 52%
House No. 2.3:
- facade installation – 45%
- K13 installation – 90%
House No. 2.6:
- window installation - 13%
House No. 2.7:
- foundation waterproofing – 50%
House No. 2.8:
- building monolith installation – 30%
Building No. 2.9:
- installation of the monolith of the building completed – 100%
AQUA Quarter, first stage
Local wastewater treatment plants:
- installation of equipment – 25%