Construction progress for July 2024
23.07.2024
Go back
Park Lake City by DIM is under construction.
We share the latest construction report for July:
VITA quarter, first line
House No. 1.3:
- filling porches with pebbles - 100%
- installation of front garden fencing - 90%
House No. 1.4:
- installation of front garden fencing - 80%
- filling porches with pebbles - 100%
House No. 1.5:
- arranging the facade of the house - 30%
- setting up self-watering - 40%
- VC installation - 10%
VITA quarter, second line
House No. 2.1:
- arrangement of electrical distribution - 98%
- screed installation - 100%
- arrangement of the ceiling of the building - 100%
- arrangement of finishing decorative plaster in MZK - 50%
- installation of front garden fencing - 50%
House No. 2.2:
- VC installation - 20%
House No. 2.3:
- arrangement of the facade - 40%
House No. 2.4:
- arrangement of porches - 100%
- backfilling with sand under the power plate - 30%
House No. 2.5:
- arrangement of porches - 100%
- arrangement of front gardens - 100%
House No. 2.6:
- backfilling with sand under the power plate - 95%
- arrangement of the power plate - 10%
House No. 2.7:
- arrangement of masonry - 80%
House No. 2.8:
- arrangement of the pit under the building - 95%
- installation of the foundation slab - 40%
House No. 2.9:
- arrangement of the monolith of the building - 60%
AQUA quarter, first line
Local treatment facilities:
- installation of metal structures - 15%