Construction progress for November 2024

05.12.2024

Go back

We share the latest construction report for November:

VITA quarter, first line

House No. 1.5:

  • external lighting of the house - 20%
  • arranging the facade of the house - 45%
  • greening of the territory - 25%

VITA quarter, second line

House No. 2.1:

  • arrangement of LCD - 97%
  • arrangement of electricity distribution - 100%
  • installation of furniture structures in MZK - 55%

House No. 2.3:

  • arrangement of the facade - 55%
  • installation K13 - 95%

House No. 2.4:

  • backfilling with sand under the power plate - 100%
  • arrangement of the power floor - 100%

House No. 2.5:

  • arrangement of the power floor - 10%

House No. 2.6:

  • installation of windows - 55%
  • installation of a monolithic treadmill - 100%
  • arrangement of front gardens - 100%

House No. 2.7:

  • installation of ventilation units - 100%
  • backfilling with sand under the power plate - 100%
  • arrangement of the power floor - 100%
  • installation of a monolithic treadmill - 100%

House No. 2.8:

  • arrangement of the monolith of the house - 33%

AQUA quarter, first line

Local treatment facilities:

  • installation of equipment - 30%