Construction progress for November 2024
05.12.2024
Go back
We share the latest construction report for November:
VITA quarter, first line
House No. 1.5:
- external lighting of the house - 20%
- arranging the facade of the house - 45%
- greening of the territory - 25%
VITA quarter, second line
House No. 2.1:
- arrangement of LCD - 97%
- arrangement of electricity distribution - 100%
- installation of furniture structures in MZK - 55%
House No. 2.3:
- arrangement of the facade - 55%
- installation K13 - 95%
House No. 2.4:
- backfilling with sand under the power plate - 100%
- arrangement of the power floor - 100%
House No. 2.5:
- arrangement of the power floor - 10%
House No. 2.6:
- installation of windows - 55%
- installation of a monolithic treadmill - 100%
- arrangement of front gardens - 100%
House No. 2.7:
- installation of ventilation units - 100%
- backfilling with sand under the power plate - 100%
- arrangement of the power floor - 100%
- installation of a monolithic treadmill - 100%
House No. 2.8:
- arrangement of the monolith of the house - 33%
AQUA quarter, first line
Local treatment facilities:
- installation of equipment - 30%