Construction progress for December 2024
30.12.2024
Go back
We share the latest construction report for December:
VITA Quarter, first phase
House No. 1.5:
- exterior lighting of the house – 23%
- arrangement of the facade of the house – 55%
- landscaping of the territory – 30%
VITA quarter, second line
House No. 2.1:
- SKD installation – 98%
- installation of furniture structures in MZK – 65%
House No. 2.3:
- facade construction – 65%
- installation K13 – 97%
House No. 2.5:
- Backfilling with sand under the power plate – 75%
House No. 2.6:
- window installation – 65%
House No. 2.8:
- installation of a monolith house – 35%
AQUA Quarter, first phase
Local treatment plants:
- equipment installation – 33%