Construction progress for December 2024

30.12.2024

Go back

We share the latest construction report for December:

VITA Quarter, first phase

House No. 1.5:

  • exterior lighting of the house – 23%
  • arrangement of the facade of the house – 55%
  • landscaping of the territory – 30%

VITA quarter, second line

House No. 2.1:

  • SKD installation – 98%
  • installation of furniture structures in MZK – 65%

House No. 2.3:

  • facade construction – 65%
  • installation K13 – 97%

House No. 2.5:

  • Backfilling with sand under the power plate – 75%

House No. 2.6:

  • window installation – 65%

House No. 2.8:

  • installation of a monolith house – 35%

AQUA Quarter, first phase

Local treatment plants:

  • equipment installation – 33%