Construction progress for February 2024
29.02.2024
Go back
Park Lake City by DIM is under construction.
We share the latest construction report for February:
VITA quarter, first line
House No. 1.5:
- Installation of windows - 97%
- External lighting of the house - 15%
VITA quarter, second line
House No. 2.1:
- Arrangement of the facade - 95%
- Installation of porcelain tiles on the facade - 98%
- Installation of screed - 99%
- Arrangement K1, K2, B1 - 98%
- Landscaping - 30%
- Arrangement of the ceiling of the main building - 95%
- Installation of the entrance door - 90%
- Installation of porcelain tiles on the floor - 80%
House No. 2.4:
- Installation of the roof - 95%
- Arrangement of facades - 50%
House No. 2.6:
- Masonry arrangement - 25%
House No. 2.7:
- Installation of geothermal wells for heat pumps - 95%
- Arrangement of 3D structures - 80%
AQUA quarter, first line
House No. 1.3:
- Masonry arrangement - 20%
Local treatment facilities:
- Arrangement of KNS - 10%