Construction progress for January 2024
31.01.2024
Go back
Park Lake City by DIM is under construction.
We share the latest construction report for January:
VITA quarter, first line
House No. 1.5:
- Installation of windows - 95%
VITA quarter, second line
House No. 2.1:
- Dilution of electricity - 95%
- Arrangement of the facade - 94%
- Installation of porcelain tiles on the facade - 95%
- Arrangement of MZK plaster - 100%
- Arrangement of heating distribution - 95%
- Arrangement of K1, K2, B1 - 95%
- Setting up external networks - 100%
- Installation of the false floor on the first floor - 90%
- Installation of porcelain tiles on the floor - 50%
House No. 2.4:
- Installation of the roof - 75%
- Arrangement of facades - 45%
House No. 2.5:
- Installation of windows - 95%
House No. 2.6:
- Masonry arrangement - 10%
House No. 2.7:
- Installation of geothermal wells for heat pumps - 85%
- Arrangement of 3D structures - 40%
House No. 2.8:
- Installation of test piles - 100%
House No. 2.9:
- Arrangement of the foundation for the building - 100%
- Installation of test piles - 100%
AQUA quarter, first line
House No. 1.1:
- Purchased vent blocks
House No. 1.3:
- Purchased material (ceramic brick) to start wall-laying works
- Purchased vent blocks