Construction progress for January 2024

31.01.2024

Go back

Park Lake City by DIM is under construction.

We share the latest construction report for January:

VITA quarter, first line

House No. 1.5:

  • Installation of windows - 95%

VITA quarter, second line

House No. 2.1:

  • Dilution of electricity - 95%
  • Arrangement of the facade - 94%
  • Installation of porcelain tiles on the facade - 95%
  • Arrangement of MZK plaster - 100%
  • Arrangement of heating distribution - 95%
  • Arrangement of K1, K2, B1 - 95%
  • Setting up external networks - 100%
  • Installation of the false floor on the first floor - 90%
  • Installation of porcelain tiles on the floor - 50%

House No. 2.4:

  • Installation of the roof - 75%
  • Arrangement of facades - 45%

House No. 2.5:

  • Installation of windows - 95%

House No. 2.6:

  • Masonry arrangement - 10%

House No. 2.7:

  • Installation of geothermal wells for heat pumps - 85%
  • Arrangement of 3D structures - 40%

House No. 2.8:

  • Installation of test piles - 100%

House No. 2.9:

  • Arrangement of the foundation for the building - 100%
  • Installation of test piles - 100%

AQUA quarter, first line

House No. 1.1:

  • Purchased vent blocks

House No. 1.3:

  • Purchased material (ceramic brick) to start wall-laying works
  • Purchased vent blocks