Construction progress for June 2024
25.06.2024
Go back
Park Lake City by DIM is under construction.
We share the latest construction report for June:
VITA quarter, first line
Playground:
- setting up self-watering - 99%
House No. 1.3:
- installation of front garden fencing - 60%
House No. 1.4:
- installation of front garden fencing - 60%
House No. 1.5:
- arranging the facade of the house - 20%
- setting up self-watering - 10%
VITA quarter, second line
House No. 2.1:
- arrangement of finishing decorative plaster in MZK - 40%
- installation of front garden fencing - 20%
House No. 2.3:
- arrangement of the power plate - 100%
- arrangement of the facade - 20%
House No. 2.4:
- arrangement of porches - 60%
- arrangement of front gardens - 100%
House No. 2.5:
- arrangement of porches - 60%
House No. 2.6:
- backfilling with sand under the power plate - 80%
- installation of ventilation units - 30%
House No. 2.7:
- arrangement of masonry - 60%
House No. 2.8:
- arranging a pit under the building - 5%
House No. 2.9:
- arrangement of the monolith of the building - 20%
AQUA quarter, first line
House No. 1.3:
- arrangement of masonry - 95%
Local treatment facilities:
- laying foundations - 90%