Construction progress for March 2024

31.03.2024

Go back

Park Lake City by DIM is under construction.

We share the latest construction report for March:

VITA quarter, second line

House No. 2.1:

  • Arrangement of LCD - 80%
  • Arrangement of K1, K2, B1 - 100%
  • Improvement - 40%
  • Installation of the entrance door - 95%

House No. 2.4:

  • Arrangement of facades - 55%

House No. 2.6:

  • Arrangement of masonry - 75%

House No. 2.7:

  • Installation of geothermal wells for heat pumps - 100%
  • Arrangement of 3D structures - 85%

AQUA quarter, first line

House No. 1.1:

  • Installation of ventilation units - 50%

Local treatment facilities:

  • Arrangement of KNS monolith - 100%