Construction progress for March 2024
31.03.2024
Go back
Park Lake City by DIM is under construction.
We share the latest construction report for March:
VITA quarter, second line
House No. 2.1:
- Arrangement of LCD - 80%
- Arrangement of K1, K2, B1 - 100%
- Improvement - 40%
- Installation of the entrance door - 95%
House No. 2.4:
- Arrangement of facades - 55%
House No. 2.6:
- Arrangement of masonry - 75%
House No. 2.7:
- Installation of geothermal wells for heat pumps - 100%
- Arrangement of 3D structures - 85%
AQUA quarter, first line
House No. 1.1:
- Installation of ventilation units - 50%
Local treatment facilities:
- Arrangement of KNS monolith - 100%