Construction progress for May 2024
21.05.2024
Go back
Park Lake City by DIM is under construction.
We share the latest construction report for May:
VITA quarter, first line
Playground:
- setting up self-watering - 96%
House No. 1.3:
- planting thuja for a green wall - 70%
- installation of front garden fencing - 50%
House No. 1.4:
- planting trees - 98%
- installation of bollards - 80%
- installation of front garden fencing - 50%
House No. 1.5:
- brickwork the whole house - 95%
- routing of EO cables according to a permanent scheme (input) - 80%
- installation of the K14 system - 95%
- installation of cables according to a permanent power supply scheme - 70%
- installation of a running track near the house - 70%
- arranging the facade of the house - 3%
VITA quarter, second line
House No. 2.1:
- arrangement of the facade - 100%
- installation of facade lighting - 100%
- landscaping - 60%
- installation of entrance doors - 100%
- false floor installation first floor - 100%
- installation of porcelain tiles on the floor - 100%
- arrangement of finishing decoration (plaster in MZK) - 10%
House No. 2.2:
- installation of porcelain tiles on the facade - 85%
- backfilling with sand under the power plate - 100%
- arrangement of the power plate - 100%
- installation of a running track - 20%
House No. 2.3:
- backfilling with sand under the power plate - 60%
House No. 2.4:
- arrangement of the facade - 57%
House No. 2.6:
- arrangement of masonry - 95%
House No. 2.8:
- arrangement of piles under the building - 100%
House No. 2.9:
- installation of technical underground - 100%
- installation of the foundation slab - 100%
AQUA quarter, first line
House No. 1.3:
- arrangement of masonry - 90%
Local treatment facilities:
- laying foundations - 85%