Construction progress for May 2024

21.05.2024

Go back

Park Lake City by DIM is under construction.

We share the latest construction report for May:

VITA quarter, first line

Playground:

  • setting up self-watering - 96%

House No. 1.3:

  • planting thuja for a green wall - 70%
  • installation of front garden fencing - 50%

House No. 1.4:

  • planting trees - 98%
  • installation of bollards - 80%
  • installation of front garden fencing - 50%

House No. 1.5:

  • brickwork the whole house - 95%
  • routing of EO cables according to a permanent scheme (input) - 80%
  • installation of the K14 system - 95%
  • installation of cables according to a permanent power supply scheme - 70%
  • installation of a running track near the house - 70%
  • arranging the facade of the house - 3%

VITA quarter, second line

House No. 2.1:

  • arrangement of the facade - 100%
  • installation of facade lighting - 100%
  • landscaping - 60%
  • installation of entrance doors - 100%
  • false floor installation first floor - 100%
  • installation of porcelain tiles on the floor - 100%
  • arrangement of finishing decoration (plaster in MZK) - 10%

House No. 2.2:

  • installation of porcelain tiles on the facade - 85%
  • backfilling with sand under the power plate - 100%
  • arrangement of the power plate - 100%
  • installation of a running track - 20%

House No. 2.3:

  • backfilling with sand under the power plate - 60%

House No. 2.4:

  • arrangement of the facade - 57%

House No. 2.6:

  • arrangement of masonry - 95%

House No. 2.8:

  • arrangement of piles under the building - 100%

House No. 2.9:

  • installation of technical underground - 100%
  • installation of the foundation slab - 100%

AQUA quarter, first line

House No. 1.3:

  • arrangement of masonry - 90%

Local treatment facilities:

  • laying foundations - 85%