Sharing a fresh construction report for December:

VITA Quarter, Phase 1

Building No.1.4:

  • parking roof installation - 100%

Building No.1.5:

  • territory landscaping - 45%
  • brickwork for entire building - 98%
  • HVAC and plumbing installation - 65%
  • plastering works - 80%
  • electrical installation in the building - 25%
  • tile installation - 20%
  • waterproofing installation - 80%

VITA Quarter, Phase 2

Building No.2.2:

  • balcony and veranda glazing - 96%

Building No.2.4:

  • facade finishing - 80%
  • floor screed installation - 20%
  • HVAC and plumbing installation - 25%
  • external building lighting - 50%

Building No.2.5:

  • roofing installation - 40%

Building No.2.6:

  • window installation - 100%

Building No.2.8:

  • internal brickwork - 45%

Building No.2.9:

  • internal brickwork - 80%

Local purification systems:

  • equipment installation - 82%