Construction progress for December 2025
05.01.2026
Go back
Sharing a fresh construction report for December:
VITA Quarter, Phase 1
Building No.1.4:
- parking roof installation - 100%
Building No.1.5:
- territory landscaping - 45%
- brickwork for entire building - 98%
- HVAC and plumbing installation - 65%
- plastering works - 80%
- electrical installation in the building - 25%
- tile installation - 20%
- waterproofing installation - 80%
VITA Quarter, Phase 2
Building No.2.2:
- balcony and veranda glazing - 96%
Building No.2.4:
- facade finishing - 80%
- floor screed installation - 20%
- HVAC and plumbing installation - 25%
- external building lighting - 50%
Building No.2.5:
- roofing installation - 40%
Building No.2.6:
- window installation - 100%
Building No.2.8:
- internal brickwork - 45%
Building No.2.9:
- internal brickwork - 80%
Local purification systems:
- equipment installation - 82%