Park Lake City
Construction progress for September 2025

01.10.2025

Go back

Sharing a fresh construction report for September:

Quarter VITA, first phase

Building No.1.5:

  • facade installation - 95%
  • external building lighting - 81%
  • floor screed - 41%

Quarter VITA, second phase

Building No.2.2:

  • VK installation - 100%
  • façade lighting installation - 100%
  • internal brickwork on the 1st floor - 100%
  • interior finishing of the building - 92%
  • door installation in apartments - 100%
  • building electrical installation - 98%
  • balcony and terrace glazing - 87%
  • low-voltage network installation - 97%
  • landscaping - 57%

Building No.2.3:

  • balcony screed installation - 74%

Building No.2.4:

  • facade installation - 58%

Building No.2.9:

  • brickwork installation - 48%