Park Lake City
Construction progress for October 2025

05.11.2025

Go back

Sharing a fresh construction report for October:

VITA Quarter, Phase 1

Building No.1.4:

  • planting trees near the building – 100%
  • parking roof installation – 50%

Building No.1.5:

  • facade installation – 99%
  • exterior building lighting – 83%
  • floor screed installation – 85%
  • installation of VK – 60%
  • territory greening – 40%

VITA Quarter, Phase 2

Building No.2.2:

  • interior building finishing – 99%
  • installation of electrical power in the building – 100%
  • balcony and terrace glazing – 95%
  • low-voltage system installation – 99%
  • irrigation system installation – 70%
  • staircase railing installation – 100%
  • territory improvement – 76%

Building No.2.3:

  • installation of K13 – 100%
  • installation of exterior building lighting – 95%
  • balcony screed installation – 77%

Building No.2.4:

  • facade installation – 62%

Building No.2.5:

  • roof installation – 19%

Building No.2.8:

  • interior brickwork – 19%

Local purification systems:

  • equipment installation – 80%