Construction progress for October 2025
05.11.2025
Go back
Sharing a fresh construction report for October:
VITA Quarter, Phase 1
Building No.1.4:
- planting trees near the building – 100%
- parking roof installation – 50%
Building No.1.5:
- facade installation – 99%
- exterior building lighting – 83%
- floor screed installation – 85%
- installation of VK – 60%
- territory greening – 40%
VITA Quarter, Phase 2
Building No.2.2:
- interior building finishing – 99%
- installation of electrical power in the building – 100%
- balcony and terrace glazing – 95%
- low-voltage system installation – 99%
- irrigation system installation – 70%
- staircase railing installation – 100%
- territory improvement – 76%
Building No.2.3:
- installation of K13 – 100%
- installation of exterior building lighting – 95%
- balcony screed installation – 77%
Building No.2.4:
- facade installation – 62%
Building No.2.5:
- roof installation – 19%
Building No.2.8:
- interior brickwork – 19%
Local purification systems:
- equipment installation – 80%