Sharing a fresh construction report for November:

Quarter VITA, phase 1

Building №1.4:

  • parking cover installation - 80%

Building №1.5:

  • facade installation - 100%
  • brickwork completion - 96%
  • HVAC and plumbing installation - 62%
  • floor screeding - 100%
  • plastering works - 20%
  • electrical installation in the building - 19%

Quarter VITA, phase 2

Building №2.2:

  • interior house finishing - 100%
  • low-voltage network installation - 100%
  • territory improvement - 87%

Building №2.4:

  • facade installation - 70%
  • floor screeding - 5%
  • HVAC and plumbing installation - 13%
  • exterior house lighting - 27%

Building №2.5:

  • jogging track installation - 75%
  • roof installation - 23%

Building №2.6:

  • window installation - 98%

Building №2.8:

  • interior brickwork - 37%

Building №2.9:

  • interior brickwork - 75%