Construction progress for November 2025
05.12.2025
Go back
Sharing a fresh construction report for November:
Quarter VITA, phase 1
Building №1.4:
- parking cover installation - 80%
Building №1.5:
- facade installation - 100%
- brickwork completion - 96%
- HVAC and plumbing installation - 62%
- floor screeding - 100%
- plastering works - 20%
- electrical installation in the building - 19%
Quarter VITA, phase 2
Building №2.2:
- interior house finishing - 100%
- low-voltage network installation - 100%
- territory improvement - 87%
Building №2.4:
- facade installation - 70%
- floor screeding - 5%
- HVAC and plumbing installation - 13%
- exterior house lighting - 27%
Building №2.5:
- jogging track installation - 75%
- roof installation - 23%
Building №2.6:
- window installation - 98%
Building №2.8:
- interior brickwork - 37%
Building №2.9:
- interior brickwork - 75%