Construction progress for February 2025

06.03.2025

Go back

Sharing a fresh construction update for February:

VITA Quarter, First Phase

Building №1.2:

  • Parking ceiling installation – 95%

Building №1.5:

  • Exterior lighting – 40%
  • Façade installation – 68%
  • Plumbing installation – 35%

VITA Quarter, Second Phase

Building №2.2:

  • Ventilation grille installation on the roof – 100%
  • Interior brickwork on the 1st floor – 40%
  • Monolithic construction (entrance group) – 70%
  • Plumbing installation – 40%

Building №2.3:

  • Ventilation grille installation on the roof – 100%
  • Façade work – 78%

Building №2.4:

  • Monolithic construction (entrance group) – 70%

Building №2.5:

  • Monolithic construction (structural slabs) – 100%
  • Monolithic construction (entrance group) – 100%

Building №2.6:

  • Window installation – 80%
  • Installation of K13 and embedded parts for refrigerant pipes – 100%

Building №2.8:

  • Running track installation – 20%
  • Monolithic construction of the building – 80%

Building №2.9:

  • Soil elevation to project level – 5%

AQUA Quarter, First Phase

Building №1.1:

  • Roof installation – 80%

Local Treatment Facilities:

  • Metal structure installation – 100%
  • Façade installation – 90%