Construction progress for February 2025
06.03.2025
Go back
Sharing a fresh construction update for February:
VITA Quarter, First Phase
Building №1.2:
- Parking ceiling installation – 95%
Building №1.5:
- Exterior lighting – 40%
- Façade installation – 68%
- Plumbing installation – 35%
VITA Quarter, Second Phase
Building №2.2:
- Ventilation grille installation on the roof – 100%
- Interior brickwork on the 1st floor – 40%
- Monolithic construction (entrance group) – 70%
- Plumbing installation – 40%
Building №2.3:
- Ventilation grille installation on the roof – 100%
- Façade work – 78%
Building №2.4:
- Monolithic construction (entrance group) – 70%
Building №2.5:
- Monolithic construction (structural slabs) – 100%
- Monolithic construction (entrance group) – 100%
Building №2.6:
- Window installation – 80%
- Installation of K13 and embedded parts for refrigerant pipes – 100%
Building №2.8:
- Running track installation – 20%
- Monolithic construction of the building – 80%
Building №2.9:
- Soil elevation to project level – 5%
AQUA Quarter, First Phase
Building №1.1:
- Roof installation – 80%
Local Treatment Facilities:
- Metal structure installation – 100%
- Façade installation – 90%