Construction progress for January 2025
01.02.2025
Go back
Sharing the latest construction report for January:
VITA Quarter, First Phase
Building No. 1.3:
- Installation of parking ceiling panels – 60%
Building No. 1.5:
- Installation of K14 system – 100%
- Facade installation – 65%
VITA Quarter, Second Phase
Building No. 2.1:
- Installation of access control system (СКД) – 99%
- Installation of furniture structures in common areas (MZK) – 100%
Building No. 2.2:
- Installation of water supply and sewage system (ВК) – 30%
Building No. 2.3:
- Facade installation – 75%
- Exterior lighting installation – 30%
Building No. 2.4:
- Roofing installation – 100%
Building No. 2.5:
- Sand filling under the structural slab – 95%
Building No. 2.6:
- Window installation – 75%
Building No. 2.8:
- Monolithic construction – 40%
- Ground elevation to project level – 20%
Building No. 2.9:
- Ground elevation to project level – 5%
AQUA Quarter, First Phase
Local wastewater treatment facilities:
- Equipment installation – 35%
- Brickwork on the roof – 90%