Sharing the latest construction report for January:

VITA Quarter, First Phase

Building No. 1.3:

  • Installation of parking ceiling panels – 60%

Building No. 1.5:

  • Installation of K14 system – 100%
  • Facade installation – 65%

VITA Quarter, Second Phase

Building No. 2.1:

  • Installation of access control system (СКД) – 99%
  • Installation of furniture structures in common areas (MZK) – 100%

Building No. 2.2:

  • Installation of water supply and sewage system (ВК) – 30%

Building No. 2.3:

  • Facade installation – 75%
  • Exterior lighting installation – 30%

Building No. 2.4:

  • Roofing installation – 100%

Building No. 2.5:

  • Sand filling under the structural slab – 95%

Building No. 2.6:

  • Window installation – 75%

Building No. 2.8:

  • Monolithic construction – 40%
  • Ground elevation to project level – 20%

Building No. 2.9:

  • Ground elevation to project level – 5%

AQUA Quarter, First Phase

Local wastewater treatment facilities:

  • Equipment installation – 35%
  • Brickwork on the roof – 90%