Park Lake City
Construction progress for March 2025

07.04.2025

Go back

Sharing fresh construction report for March:

Quarter VITA, first phase

Building №1.2:

  • installation of parking spaces - 100%

Building №1.5:

  • laying of EO cables according to the permanent scheme (input) - 100%
  • facade installation of the building - 75%
  • landscaping of the territory - 10%

Quarter VITA, second phase

Building №2.2:

  • installation of running track - 100%
  • facade installation of the building - 95%
  • internal brickwork of the 1st floor - 45%
  • monolithic construction (entrance group) - 100%
  • installation of VK - 60%
  • interior finishing of the building - 2%
  • installation of electricity supply in the building - 50%
  • installation of external networks - 5%

Building №2.3:

  • facade installation - 92%

Building №2.4:

  • monolithic construction (entrance group) - 100%

Building №2.6:

  • installation of windows - 90%

Building №2.8:

  • installation of running track - 40%
  • monolithic construction of the building - 95%
  • ground lifting to the design mark - 85%

Local sewage treatment plants:

  • facade installation - 95%