Construction progress for March 2025
07.04.2025
Go back
Sharing fresh construction report for March:
Quarter VITA, first phase
Building №1.2:
- installation of parking spaces - 100%
Building №1.5:
- laying of EO cables according to the permanent scheme (input) - 100%
- facade installation of the building - 75%
- landscaping of the territory - 10%
Quarter VITA, second phase
Building №2.2:
- installation of running track - 100%
- facade installation of the building - 95%
- internal brickwork of the 1st floor - 45%
- monolithic construction (entrance group) - 100%
- installation of VK - 60%
- interior finishing of the building - 2%
- installation of electricity supply in the building - 50%
- installation of external networks - 5%
Building №2.3:
- facade installation - 92%
Building №2.4:
- monolithic construction (entrance group) - 100%
Building №2.6:
- installation of windows - 90%
Building №2.8:
- installation of running track - 40%
- monolithic construction of the building - 95%
- ground lifting to the design mark - 85%
Local sewage treatment plants:
- facade installation - 95%