Sharing a fresh construction report for May:

VITA block, phase two

Building No.2.2:

  • facade installation - 100%
  • ceramic granite tile facade installation - 98%
  • VK installation - 70%
  • interior finishing of the building - 23%
  • electric power installation in the building - 59%

Building No.2.3:

  • external lighting installation - 33%

Building No.2.6:

  • window installation - 93%

Building No.2.8:

  • building monolith arrangement - 100%
  • ground elevation to design mark - 93%
  • jogging track arrangement - 50%

Building No.2.9:

  • ground elevation to design mark - 93%

Local treatment facilities:

  • equipment installation - 40%