Construction progress for May 2025
02.06.2025
Go back
Sharing a fresh construction report for May:
VITA block, phase two
Building No.2.2:
- facade installation - 100%
- ceramic granite tile facade installation - 98%
- VK installation - 70%
- interior finishing of the building - 23%
- electric power installation in the building - 59%
Building No.2.3:
- external lighting installation - 33%
Building No.2.6:
- window installation - 93%
Building No.2.8:
- building monolith arrangement - 100%
- ground elevation to design mark - 93%
- jogging track arrangement - 50%
Building No.2.9:
- ground elevation to design mark - 93%
Local treatment facilities:
- equipment installation - 40%