Construction progress for August 2025
03.09.2025
Go back
Sharing a fresh construction report for August:
Quarter VITA, first phase
Building No.1.4:
- parking cover installation - 40%
Building No.1.5:
- building facade finishing - 81%
- building exterior lighting - 49%
- floor screeding - 37%
Quarter VITA, second phase
Building No.2.2:
- HVAC installation - 95%
- ceramic tile facade installation - 100%
- interior finishing - 81%
- apartment door installation - 98%
- exterior utility installation - 100%
- low-current systems installation - 83%
- automatic watering system installation - 53%
- staircase railing installation - 40%
- territory improvement - 45%
Building No.2.3:
- exterior lighting installation - 91%
- balcony screeding - 72%
Building No.2.7:
- foundation waterproofing - 100%
Building No.2.9:
- brickwork - 20%
Local purification facilities:
- roof brickwork - 100%
- equipment installation - 75%