Construction progress for June 2025
02.07.2025
Go back
Sharing a fresh construction report for June:
Quarter VITA, first phase
Building No.1.5:
- installation of water supply and sewerage systems – 45%
- landscaping – 35%
Quarter VITA, second phase
Building No.2.2:
- installation of water supply and sewerage systems – 75%
- internal brickwork on the first floor – 65%
- interior finishing of the building – 50%
- installation of doors in apartments – 50%
- electrical installation in the building – 80%
- external network installation – 20%
- installation of glass structures on balconies and terraces – 75%
- low-voltage network installation – 50%
- installation of automatic irrigation system – 35%
Building No.2.3:
- installation of external lighting – 70%
Building No.2.7:
- insulation of the basement – 40%
Building No.2.9:
- ground elevation to design level – 60%
Local wastewater treatment facilities:
- foundation construction – 98%