Sharing a fresh construction report for June:

Quarter VITA, first phase

Building No.1.5:

  • installation of water supply and sewerage systems – 45%
  • landscaping – 35%

Quarter VITA, second phase

Building No.2.2:

  • installation of water supply and sewerage systems – 75%
  • internal brickwork on the first floor – 65%
  • interior finishing of the building – 50%
  • installation of doors in apartments – 50%
  • electrical installation in the building – 80%
  • external network installation – 20%
  • installation of glass structures on balconies and terraces – 75%
  • low-voltage network installation – 50%
  • installation of automatic irrigation system – 35%

Building No.2.3:

  • installation of external lighting – 70%

Building No.2.7:

  • insulation of the basement – 40%

Building No.2.9:

  • ground elevation to design level – 60%

Local wastewater treatment facilities:

  • foundation construction – 98%