Park Lake City
Construction progress for April 2026

30.04.2026

Go back

Sharing the latest construction progress report for April:

VITA Quarter, Phase 1

Building No. 1.5:

  • installation of HVAC and plumbing – 85%
  • open-type garages – 55%
  • installation of electrical systems in the building – 80%
  • tile installation – 85%
  • drywall installation – 75%
  • wall and ceiling surface puttying – 91%
  • external building lighting – 87%

VITA Quarter, Phase 2

Building No. 2.1:

  • installation of decorative paving elements – 62%

Building No. 2.2:

  • landscaping works – 95%
  • installation of automatic irrigation – 80%

Building No. 2.3:

  • installation of HVAC and plumbing – 3%
  • floor screed installation – 60%

Building No. 2.4:

  • facade works – 95%
  • external building lighting – 80%
  • installation of HVAC and plumbing – 40%
  • floor screed installation – 75%

Building No. 2.8:

internal brickwork – 55%

AQUA Quarter

Building No. 1.1:

  • building glazing – 27%
  • sand bedding under reinforced concrete slab – 100%

Building No. 1.2:

  • excavation soil replacement – 100%

Building No. 1.3:

  • sand bedding under reinforced concrete slab – 15%

Building No. 1.4:

excavation soil replacement – 100%