Construction progress for April 2026
30.04.2026
Go back
Sharing the latest construction progress report for April:
VITA Quarter, Phase 1
Building No. 1.5:
- installation of HVAC and plumbing – 85%
- open-type garages – 55%
- installation of electrical systems in the building – 80%
- tile installation – 85%
- drywall installation – 75%
- wall and ceiling surface puttying – 91%
- external building lighting – 87%
VITA Quarter, Phase 2
Building No. 2.1:
- installation of decorative paving elements – 62%
Building No. 2.2:
- landscaping works – 95%
- installation of automatic irrigation – 80%
Building No. 2.3:
- installation of HVAC and plumbing – 3%
- floor screed installation – 60%
Building No. 2.4:
- facade works – 95%
- external building lighting – 80%
- installation of HVAC and plumbing – 40%
- floor screed installation – 75%
Building No. 2.8:
internal brickwork – 55%
AQUA Quarter
Building No. 1.1:
- building glazing – 27%
- sand bedding under reinforced concrete slab – 100%
Building No. 1.2:
- excavation soil replacement – 100%
Building No. 1.3:
- sand bedding under reinforced concrete slab – 15%
Building No. 1.4:
excavation soil replacement – 100%