Construction Progress for August 2026

03.09.2026

Go back

Sharing the latest construction progress report for August:

VITA Quarter, Phase 1

Building No. 1.4

  • Open-type garages — 90%

Building No. 1.5

  • Open-type garages — 80%
  • Landscaping works — 80%
  • Low-current systems — 100%
  • Installation of FEM paving elements — 85%

VITA Quarter, Phase 2

Building No. 2.3

  • Installation of HVAC, water supply and sewerage systems — 50%
  • Masonry works — 95%
  • ETR installation — 50%
  • Video surveillance system installation — 25%

Building No. 2.4

  • Installation of HVAC, water supply and sewerage systems — 60%
  • Façade works — 100%

Building No. 2.5

  • Roofing works — 95%
  • Façade works — 50%

Building No. 2.6

  • Roofing works — 50%
  • Façade works — 45%

Building No. 2.8

  • Internal brickwork — 70%

AQUA Quarter

Building No. 1.1

  • Building glazing — 99%

Building No. 1.3

  • Installation of power electrical systems — 5%
  • Building glazing — 65%

Building No. 1.4

  • Monolithic concrete works — 65%