Construction Progress for August 2026
03.09.2026
Go back
Sharing the latest construction progress report for August:
VITA Quarter, Phase 1
Building No. 1.4
- Open-type garages — 90%
Building No. 1.5
- Open-type garages — 80%
- Landscaping works — 80%
- Low-current systems — 100%
- Installation of FEM paving elements — 85%
VITA Quarter, Phase 2
Building No. 2.3
- Installation of HVAC, water supply and sewerage systems — 50%
- Masonry works — 95%
- ETR installation — 50%
- Video surveillance system installation — 25%
Building No. 2.4
- Installation of HVAC, water supply and sewerage systems — 60%
- Façade works — 100%
Building No. 2.5
- Roofing works — 95%
- Façade works — 50%
Building No. 2.6
- Roofing works — 50%
- Façade works — 45%
Building No. 2.8
- Internal brickwork — 70%
AQUA Quarter
Building No. 1.1
- Building glazing — 99%
Building No. 1.3
- Installation of power electrical systems — 5%
- Building glazing — 65%
Building No. 1.4
- Monolithic concrete works — 65%