Park Lake City
Construction Progress — October 2026

02.11.2026

Go back

Construction Continues — October Progress in the VITA and AQUA Neighborhoods

Here is an overview of the construction progress achieved in October.

VITA Neighborhood, Phase 1

Building No. 1.4

  • Open garages — 95%

Building No. 1.5

  • Automatic irrigation system installation — 75%

  • Landscaping — 85%

  • Open garages — 95%

VITA Neighborhood, Phase 2

Building No. 2.3

  • Installation of heating, ventilation, water supply and sewage systems — 63%

  • Floor screeding — 80%

  • Electrical installation works — 40%

  • Installation of glass terrace railings — 60%

Building No. 2.4

  • Installation of heating, ventilation, water supply and sewage systems — 50%

  • Exterior building lighting — 90%

  • Electrical installation works — 55%

Building No. 2.5

  • Facade works — 60%

  • Exterior building lighting — 25%

Building No. 2.6

  • Facade works — 55%

  • Exterior building lighting — 10%

Building No. 2.8

  • Interior brickwork — 80%

AQUA Neighborhood

  • Building glazing — 100%

Building No. 1.3

  • Sand backfilling beneath structural floor slabs in apartments — 95%

  • Building glazing — 90%

Building No. 1.4

  • Monolithic concrete construction — 90%

Local Wastewater Treatment Facilities

  • Equipment installation — 99%

We build responsibly, step by step, bringing closer the moment when new residents move into their homes.