Construction Progress — October 2026
02.11.2026
Construction Continues — October Progress in the VITA and AQUA Neighborhoods
Here is an overview of the construction progress achieved in October.
VITA Neighborhood, Phase 1
Building No. 1.4
Open garages — 95%
Building No. 1.5
Automatic irrigation system installation — 75%
Landscaping — 85%
Open garages — 95%
VITA Neighborhood, Phase 2
Building No. 2.3
Installation of heating, ventilation, water supply and sewage systems — 63%
Floor screeding — 80%
Electrical installation works — 40%
Installation of glass terrace railings — 60%
Building No. 2.4
Installation of heating, ventilation, water supply and sewage systems — 50%
Exterior building lighting — 90%
Electrical installation works — 55%
Building No. 2.5
Facade works — 60%
Exterior building lighting — 25%
Building No. 2.6
Facade works — 55%
Exterior building lighting — 10%
Building No. 2.8
Interior brickwork — 80%
AQUA Neighborhood
Building glazing — 100%
Building No. 1.3
Sand backfilling beneath structural floor slabs in apartments — 95%
Building glazing — 90%
Building No. 1.4
Monolithic concrete construction — 90%
Local Wastewater Treatment Facilities
Equipment installation — 99%
We build responsibly, step by step, bringing closer the moment when new residents move into their homes.