Construction Progress — September 2026

09.10.2026

Go back

Construction Continues — September Progress in the VITA and AQUA Neighborhoods

Step by step, the buildings are taking on their finished appearance, while the surrounding areas are gaining the details that will shape the future living environment.

  • In Phase 1 of the VITA neighborhood, we are working on engineering systems and landscaping.
  • In Phase 2, we continue facade and roofing works, utility network installation, and terrace railing installation.
  • In the AQUA neighborhood, construction activities include foundation works, reinforced concrete structures, glazing, and waterproofing.

Here is our construction progress report for September .

VITA Neighborhood, Phase 1

Building No. 1.4

- Construction of open-type garages is 95% complete.

Building No. 1.5

  • Installation of exterior building lighting has been completed.

  • Construction of open-type garages is 90% complete.

  • Landscaping works are ongoing, with 85% completed.

  • Installation of electrical equipment in the building is 99% complete.

  • Tile installation has been completed.

  • Installation of low-voltage systems is 99% complete.

  • Installation of paving stones continues, with 75% of the work completed.

VITA Neighborhood, Phase 2

Building No. 2.3

  • Facade works are 99% complete.

  • Installation of heating, ventilation, water supply, and sewage systems is 60% complete.

  • Electrical works are 20% complete.

  • Installation of the video surveillance system is 15% complete.

  • Installation of glass terrace railings continues, with 10% of the work completed.

  • Masonry works are 95% complete.

Building No. 2.4

  • Facade works have been completed.

  • Installation of heating, ventilation, water supply, and sewage systems is 46% complete.

Building No. 2.5

  • Roofing works are 85% complete.

  • Facade works are 55% complete.

  • Installation of exterior building lighting is 20% complete.

Building No. 2.6

  • Facade works are 50% complete.

  • Roofing works are 95% complete.

  • Installation of exterior building lighting is 3% complete.

Building No. 2.8

- Interior brickwork is 75% complete.

Building No. 2.9

- Work to raise the ground level to the specified design elevation continues, with 80% completed.

AQUA Neighborhood

Building No. 1.1

  • Building glazing is 95% complete.

  • Sand backfilling beneath structural slabs in the apartments has been completed.

  • Roofing works have been completed.

  • Building waterproofing works are ongoing.

Building No. 1.2

- Foundation slab construction has been completed.

Building No. 1.3

  • Sand backfilling beneath structural slabs in the apartments is 95% complete.

  • Building glazing is 75% complete.

Building No. 1.4

- Reinforced concrete structural works are 75% complete.

Local Wastewater Treatment Facilities

- Equipment installation is 99% complete.

Every change on the construction site reflects the team's daily efforts — from foundations and utility networks to lighting and walkway paving. We continue building and keeping you infor med about the progress achieved at every stage.