Construction progress for July 2026
03.08.2026
Sharing the latest construction progress report for July:
VITA Quarter – Phase One
Building 1.4
Open-type garages – 85% complete.
Building 1.5
External building lighting – 100% complete;
Open-type garages – 75% complete;
Landscaping works – 70% complete;
Installation of engineering equipment – 99% complete;
Tile installation – 100% complete;
Low-voltage systems – 99% complete;
Paving stone installation – 75% complete.
VITA Quarter – Phase Two
Building 2.3
Façade works – 99% complete;
HVAC and water supply & sewerage (MEP) installation – 20% complete;
Masonry works – 90% complete.
Building 2.4
Masonry works – 100% complete;
HVAC and water supply & sewerage (MEP) installation – 46% complete.
Building 2.5
Roofing works – 85% complete;
Façade works – 20% complete;
External building lighting – 8% complete.
Building 2.6
Façade works – 17% complete.
Building 2.8
Internal brick masonry – 65% complete.
Building 2.9
Earthworks (raising the ground to the design elevation) – 80% complete.
AQUA Quarter
Building 1.1
Glazing – 95% complete;
Sand backfilling beneath floor slabs in apartments – 100% complete;
Waterproofing works – 20% complete;
Roofing works – 100% complete.
Building 1.3
Sand backfilling beneath floor slabs in apartments – 95% complete;
Glazing – 50% complete.
Building 1.4
Monolithic concrete works – 45% complete.
WWTP (Local Wastewater Treatment Plant)
Equipment installation – 99% complete.