Construction progress for July 2026

03.08.2026

Go back

Sharing the latest construction progress report for July:

VITA Quarter – Phase One

Building 1.4

  • Open-type garages – 85% complete.

Building 1.5

  • External building lighting – 100% complete;

  • Open-type garages – 75% complete;

  • Landscaping works – 70% complete;

  • Installation of engineering equipment – 99% complete;

  • Tile installation – 100% complete;

  • Low-voltage systems – 99% complete;

  • Paving stone installation – 75% complete.

VITA Quarter – Phase Two

Building 2.3

  • Façade works – 99% complete;

  • HVAC and water supply & sewerage (MEP) installation – 20% complete;

  • Masonry works – 90% complete.

Building 2.4

  • Masonry works – 100% complete;

  • HVAC and water supply & sewerage (MEP) installation – 46% complete.

Building 2.5

  • Roofing works – 85% complete;

  • Façade works – 20% complete;

  • External building lighting – 8% complete.

Building 2.6

  • Façade works – 17% complete.

Building 2.8

  • Internal brick masonry – 65% complete.

Building 2.9

  • Earthworks (raising the ground to the design elevation) – 80% complete.

AQUA Quarter

Building 1.1

  • Glazing – 95% complete;

  • Sand backfilling beneath floor slabs in apartments – 100% complete;

  • Waterproofing works – 20% complete;

  • Roofing works – 100% complete.

Building 1.3

  • Sand backfilling beneath floor slabs in apartments – 95% complete;

  • Glazing – 50% complete.

Building 1.4

  • Monolithic concrete works – 45% complete.

WWTP (Local Wastewater Treatment Plant)

  • Equipment installation – 99% complete.