Construction progress for March 2026
02.04.2026
Go back
Sharing a fresh construction report for March:
Quarter VITA, phase 1
Building №1.5:
- installation of heating and plumbing systems - 80%
- installation of electrical wiring in the building - 65%
- tiling - 75%
- installation of drywall - 50%
- wall and ceiling surface finishing - 90%
- manufacturing and installation of ventilation grilles on the roof - 100%
Quarter VITA, phase 2
Building №2.1:
- laying of decorative paving elements - 25%
Building №2.2:
- landscaping of the area - 88%
Building №2.4:
- brickwork - 100%
- exterior lighting of the building - 75%
Building №2.5:
- roofing - 45%
Building №2.8:
- interior brickwork - 50%
Quarter AQUA
Building №1.1:
- brickwork - 98%
- roofing - 85%
- building glazing - 5%
Building №1.2:
- underground foundation replacement - 55%