Construction progress for March 2026

02.04.2026

Go back

Sharing a fresh construction report for March:

Quarter VITA, phase 1

Building №1.5:

  • installation of heating and plumbing systems - 80%
  • installation of electrical wiring in the building - 65%
  • tiling - 75%
  • installation of drywall - 50%
  • wall and ceiling surface finishing - 90%
  • manufacturing and installation of ventilation grilles on the roof - 100%

Quarter VITA, phase 2

Building №2.1:

  • laying of decorative paving elements - 25%

Building №2.2:

  • landscaping of the area - 88%

Building №2.4:

  • brickwork - 100%
  • exterior lighting of the building - 75%

Building №2.5:

  • roofing - 45%

Building №2.8:

  • interior brickwork - 50%

Quarter AQUA

Building №1.1:

  • brickwork - 98%
  • roofing - 85%
  • building glazing - 5%

Building №1.2:

  • underground foundation replacement - 55%