Construction progress for January 2026
29.01.2026
Go back
Sharing a fresh construction report for January:
VITA Quarter, first phase
Building №1.5:
- brickwork throughout the building - 100%
- installation of water supply and heating systems - 70%
- plastering works - 100%
- electrical installation in the building - 45%
- tiling works - 30%
- waterproofing - 100%
VITA Quarter, second phase
Building №2.2:
- balcony and terrace glazing - 98%
Building №2.3:
- balcony screed installation - 100%
Building №2.8:
- internal brickwork - 48%
Building №2.9:
- internal brickwork - 82%
Local sewage treatment systems:
- equipment installation - 84%