Construction progress for January 2026

29.01.2026

Go back

Sharing a fresh construction report for January:

VITA Quarter, first phase

Building №1.5:

  • brickwork throughout the building - 100%
  • installation of water supply and heating systems - 70%
  • plastering works - 100%
  • electrical installation in the building - 45%
  • tiling works - 30%
  • waterproofing - 100%

VITA Quarter, second phase

Building №2.2:

  • balcony and terrace glazing - 98%

Building №2.3:

  • balcony screed installation - 100%

Building №2.8:

  • internal brickwork - 48%

Building №2.9:

  • internal brickwork - 82%

Local sewage treatment systems:

  • equipment installation - 84%