Construction progress in February 2026

04.03.2026

Go back

Sharing a fresh report on construction for February:

VITA neighborhood, phase 1

Building No. 1.5:

  • HVAC and water supply installation – 73%
  • EO installation in the building – 50%
  • tiling – 50%
  • drywall installation – 40%
  • wall and ceiling painting – 40%
  • manufacture and installation of roof ventilation grilles – 70%

VITA neighborhood, phase 2

Building No. 2.4:

  • brickwork – 96%

Building No. 2.5:

  • brickwork – 98%

AQUA neighborhood

Building No. 1.1:

  • brickwork – 96%