Construction progress in February 2026
04.03.2026
Go back
Sharing a fresh report on construction for February:
VITA neighborhood, phase 1
Building No. 1.5:
- HVAC and water supply installation – 73%
- EO installation in the building – 50%
- tiling – 50%
- drywall installation – 40%
- wall and ceiling painting – 40%
- manufacture and installation of roof ventilation grilles – 70%
VITA neighborhood, phase 2
Building No. 2.4:
- brickwork – 96%
Building No. 2.5:
- brickwork – 98%
AQUA neighborhood
Building No. 1.1:
- brickwork – 96%