Construction progress for July 2024

05.08.2024

Go back

THE ONE construction results for July:

  • Earthworks - 76%
  • Sheet metal fence - 100%
  • Reinforcement of the sheet pile fence - 90%
  • Preparatory works for strengthening the pit - 59%
  • Installation of the fence - 79%
  • Installation of beam reinforcement - 93%
  • Implementation of the pile test program - 100%
  • Piling field arrangement – 27%