Construction progress for November 2024
05.12.2024
Go back
THE ONE construction results for November:
- extraction of soil up to the design mark of the construction of the foundation of the building from the mark 153.7 – 41%
- waterproofing works of the lower left vertical part of the stylobate on prepared hooks - 100%
- the monolithic frame of the lower left vertical part of the stylobate -6, -5 floor - 100% (510 m3 of concrete) was completed
- production of a sheet-pile reinforcement beam - 40% (more than 120 m3 of concrete)
- the installation of the tower crane has been completed
- we continue the installation of piles of the main pile field - 31 piles
- installation of a monolithic fence - 110 m3