THE ONE
Construction progress for September 2024

08.10.2024

Go back

Construction results THE ONE for September:

  • pouring the foundation of the left part of the building - 100% (over 600 m3 of concrete)
  • arrangement of concrete preparation according to the work plan - 100%
  • preparation and compaction of the soil for the foundation of the left part of the building - 90%
  • waterproofing works on prepared screeds — 90%
  • manufacture of the sheet-pile reinforcement beam — 30% (over 100 m3 of concrete)
  • extraction of soil up to the design mark of the construction of the foundation of the building from the mark 153.7 — 30%
  • the installation of piles of the main pile field continues — 10 frames have been made
  • installation of the tower crane has begun