Construction progress for December 2024

06.01.2025

Go back

THE ONE construction results for December:

  • installation of piles for the high-rise part of the house – 27 pieces
  • manufacturing of sheet pile fence reinforcement beam – 70%
  • poured – 826.4 m3 of concrete

Lower left part of the stylobate:

  • reinforcement of vertical elements -4th floor – 100%
  • installation of formwork for vertical elements -4th floor – 100%
  • concreting of vertical elements -4th floor – 100%
  • installation of formwork for the floor slab -4th floor – 100%
  • concreting of the floor slab -4th floor – 100%
  • reinforcement of vertical elements of the floor -3 – 100%
  • concreting of vertical elements -3rd floor – 100%
  • installation of formwork for the floor slab -3rd floor – 100%
  • fence installation – 28%
  • installation of bentonite mats on a vertical surface – 100%
  • installation of a hydraulic joint in cold joints – 100%

Arrangement of the pit of the upper part of the right stylobate:

  • development and removal of soil over 900 m3
  • pile cleaning – 100%
  • fence formwork installation – 100%
  • fence reinforcement – 100%
  • concreting of the fence – 100%
  • concrete preparation facility – 100%
  • installation of bentonite mats on a vertical surface
  • installation of a hydraulic wedge on cold joints
  • reinforcement of the foundation slab – 100%
  • concreting of the foundation slab – 100%
  • reinforcement of vertical elements -6th floor – 100%