Construction progress for December 2024
06.01.2025
Go back
THE ONE construction results for December:
- installation of piles for the high-rise part of the house – 27 pieces
- manufacturing of sheet pile fence reinforcement beam – 70%
- poured – 826.4 m3 of concrete
Lower left part of the stylobate:
- reinforcement of vertical elements -4th floor – 100%
- installation of formwork for vertical elements -4th floor – 100%
- concreting of vertical elements -4th floor – 100%
- installation of formwork for the floor slab -4th floor – 100%
- concreting of the floor slab -4th floor – 100%
- reinforcement of vertical elements of the floor -3 – 100%
- concreting of vertical elements -3rd floor – 100%
- installation of formwork for the floor slab -3rd floor – 100%
- fence installation – 28%
- installation of bentonite mats on a vertical surface – 100%
- installation of a hydraulic joint in cold joints – 100%
Arrangement of the pit of the upper part of the right stylobate:
- development and removal of soil over 900 m3
- pile cleaning – 100%
- fence formwork installation – 100%
- fence reinforcement – 100%
- concreting of the fence – 100%
- concrete preparation facility – 100%
- installation of bentonite mats on a vertical surface
- installation of a hydraulic wedge on cold joints
- reinforcement of the foundation slab – 100%
- concreting of the foundation slab – 100%
- reinforcement of vertical elements -6th floor – 100%