Construction progress for October 2024
04.11.2024
Go back
THE ONE construction results for October:
- a tower crane was installed
- removed and transported the soil - about 2000 m³
- built -6 over the left stylobate
- waterproofing of the 6th floor of the left stylobate has been completed
- preparatory work has been done on the execution of works on the right stylobate
- work on strengthening the sheet pile fence has been completed
- mounted metal sheet pile fence
- 41 piling piles have been installed