Construction progress for October 2024

04.11.2024

Go back

THE ONE construction results for October:

  • a tower crane was installed
  • removed and transported the soil - about 2000 m³
  • built -6 over the left stylobate
  • waterproofing of the 6th floor of the left stylobate has been completed
  • preparatory work has been done on the execution of works on the right stylobate
  • work on strengthening the sheet pile fence has been completed
  • mounted metal sheet pile fence
  • 41 piling piles have been installed