THE ONE
Construction Progress for February 2025

07.03.2025

Go back

THE ONE construction results for February 2025:

Lower left part of the stylobate:

  • installation of formwork for floor slab -1 floor – 100%
  • reinforcement of floor slab -1 floor – 100%
  • concreting of floor slab -1 floor – 100%
  • reinforcement of vertical elements of parapet -1 floor – 70%
  • reinforcement of parapet -1 floor – 100%
  • concreting of parapet -1 floor – 80%
  • reinforcement of pool 1 floor – 70%
  • concreting of pool – 80%
  • waterproofing of pool – 100%
  • reinforcement of vertical elements of 1 floor – 90%
  • installation of KAB hydro-key, pool

Upper left part of the stylobate:

  • excavation of soil: 400 m3
  • installation of fence – 100%
  • installation of concrete preparation – 100%

Upper part of the right stylobate:

  • installation of bentonite mats on the vertical surface – 100%
  • installation of hydraulic dowels on cold joints – 100%
  • dismantling of the beam for strengthening the sheet pile fence – 100%
  • reinforcement of vertical elements -5th floor – 100%
  • concreting of -5th floor – 100%
  • reinforcement of vertical elements -4th floor – 100%
  • concreting of vertical elements -4th floor – 100%
  • manufacturing of the beam for strengthening the sheet pile fence – 100%
  • manufacturing of metal struts for strengthening the sheet pile fence – 100%
  • installation of the fence – 68%
  • installation of piles – 14 pcs.
  • the embankment field is 100% completed
  • poured in February – 375 m3 of concrete