Construction Progress for February 2025
07.03.2025
Go back
THE ONE construction results for February 2025:
Lower left part of the stylobate:
- installation of formwork for floor slab -1 floor – 100%
- reinforcement of floor slab -1 floor – 100%
- concreting of floor slab -1 floor – 100%
- reinforcement of vertical elements of parapet -1 floor – 70%
- reinforcement of parapet -1 floor – 100%
- concreting of parapet -1 floor – 80%
- reinforcement of pool 1 floor – 70%
- concreting of pool – 80%
- waterproofing of pool – 100%
- reinforcement of vertical elements of 1 floor – 90%
- installation of KAB hydro-key, pool
Upper left part of the stylobate:
- excavation of soil: 400 m3
- installation of fence – 100%
- installation of concrete preparation – 100%
Upper part of the right stylobate:
- installation of bentonite mats on the vertical surface – 100%
- installation of hydraulic dowels on cold joints – 100%
- dismantling of the beam for strengthening the sheet pile fence – 100%
- reinforcement of vertical elements -5th floor – 100%
- concreting of -5th floor – 100%
- reinforcement of vertical elements -4th floor – 100%
- concreting of vertical elements -4th floor – 100%
- manufacturing of the beam for strengthening the sheet pile fence – 100%
- manufacturing of metal struts for strengthening the sheet pile fence – 100%
- installation of the fence – 68%
- installation of piles – 14 pcs.
- the embankment field is 100% completed
- poured in February – 375 m3 of concrete