Construction results of THE ONE for November 2025:

Main building:

  • concreting of vertical structures -2nd floor — 100%
  • slab reinforcement -2nd floor — 100%
  • concreting of slab -2nd floor — 100%
  • vertical structure reinforcement -1st floor — 100%
  • concreting of vertical structures -1st floor — 100%
  • slab reinforcement -1st floor — 100%
  • concreting of slab -1st floor — 100%
  • vertical structure reinforcement 1st floor — 90%
  • concreting of vertical structures 1st floor — 80%
  • installation of precast concrete stairs and platforms on the -6th floor — 100%
  • installation of precast concrete stairs and platforms on the -5th floor — 100%
  • installation of precast concrete stairs and platforms on the -4th floor — 100%
  • installation of precast concrete stairs and platforms on the -3rd floor — 100%
  • installation of precast concrete stairs and platforms on the -2nd floor — 100%
  • installation of precast concrete stairs and platforms on the -1st floor — 100%

Left stylobate:

  • vertical structure reinforcement -2nd floor — 100%
  • concreting of vertical structures -2nd floor — 50%
  • installation of bentonite mats on the vertical surface -2nd floor — 100%
  • installation of hydro insulation at cold joints -2nd floor — 100%

Right stylobate:

  • vertical structure reinforcement -1st floor — 50%
  • concreting of vertical structures -1st floor — 50%
  • formwork for slab -1st floor — 50%

Completed for November — 398 m3 of reinforced concrete building frame structures.