Construction progress for November 2025
05.12.2025
Go back
Construction results of THE ONE for November 2025:
Main building:
- concreting of vertical structures -2nd floor — 100%
- slab reinforcement -2nd floor — 100%
- concreting of slab -2nd floor — 100%
- vertical structure reinforcement -1st floor — 100%
- concreting of vertical structures -1st floor — 100%
- slab reinforcement -1st floor — 100%
- concreting of slab -1st floor — 100%
- vertical structure reinforcement 1st floor — 90%
- concreting of vertical structures 1st floor — 80%
- installation of precast concrete stairs and platforms on the -6th floor — 100%
- installation of precast concrete stairs and platforms on the -5th floor — 100%
- installation of precast concrete stairs and platforms on the -4th floor — 100%
- installation of precast concrete stairs and platforms on the -3rd floor — 100%
- installation of precast concrete stairs and platforms on the -2nd floor — 100%
- installation of precast concrete stairs and platforms on the -1st floor — 100%
Left stylobate:
- vertical structure reinforcement -2nd floor — 100%
- concreting of vertical structures -2nd floor — 50%
- installation of bentonite mats on the vertical surface -2nd floor — 100%
- installation of hydro insulation at cold joints -2nd floor — 100%
Right stylobate:
- vertical structure reinforcement -1st floor — 50%
- concreting of vertical structures -1st floor — 50%
- formwork for slab -1st floor — 50%
Completed for November — 398 m3 of reinforced concrete building frame structures.