Construction results of THE ONE for September 2025:

Main building:

  • Reinforcement of vertical structures -3rd floor - 80%
  • Concrete pouring of vertical structures -3rd floor - 80%
  • Installation of bentonite mats on vertical surface -3rd floor - 100%
  • Installation of hydro insulation on cold joints -3rd floor - 100%
  • Reinforcement of slab -3rd floor - 80%
  • Concrete pouring of slab -3rd floor - 80%
  • Reinforcement of vertical structures -2nd floor - 70%
  • Concrete pouring of vertical structures -2nd floor - 70%
  • Reinforcement of slab -2nd floor - 65%
  • Concrete pouring of slab -2nd floor - 65%
  • Reinforcement of vertical structures -1st floor - 60%
  • Concrete pouring of vertical structures -1st floor - 60%
  • Reinforcement of slab -1st floor - 55%
  • Concrete pouring of slab -1st floor - 55%

Completed in September - 505 m3 of reinforced concrete building structures.