Construction progress for September 2025
01.10.2025
Go back
Construction results of THE ONE for September 2025:
Main building:
- Reinforcement of vertical structures -3rd floor - 80%
- Concrete pouring of vertical structures -3rd floor - 80%
- Installation of bentonite mats on vertical surface -3rd floor - 100%
- Installation of hydro insulation on cold joints -3rd floor - 100%
- Reinforcement of slab -3rd floor - 80%
- Concrete pouring of slab -3rd floor - 80%
- Reinforcement of vertical structures -2nd floor - 70%
- Concrete pouring of vertical structures -2nd floor - 70%
- Reinforcement of slab -2nd floor - 65%
- Concrete pouring of slab -2nd floor - 65%
- Reinforcement of vertical structures -1st floor - 60%
- Concrete pouring of vertical structures -1st floor - 60%
- Reinforcement of slab -1st floor - 55%
- Concrete pouring of slab -1st floor - 55%
Completed in September - 505 m3 of reinforced concrete building structures.