Construction progress for December 2025

05.01.2026

Go back

Construction results of THE ONE for December 2025:

Main building:

  • reinforcement and concreting of vertical structures of the 1st floor - 100%
  • reinforcement and concreting of the slab of the 1st floor - 100%
  • reinforcement and concreting of vertical structures of the 2nd floor - 100%
  • reinforcement and concreting of the slab of the 2nd floor - 100%
  • reinforcement of vertical structures of the 3rd floor - 40%
  • concreting of vertical structures of the 3rd floor - 30%
  • installation of prefabricated reinforced concrete stairs and platforms on the 1st floor - 100%

Left podium:

  • concreting of vertical structures of the -2nd floor - 100%

Right podium:

  • reinforcement and concreting of vertical structures of the -1st floor - 55%
  • formwork of the slab of the -1st floor - 50%

Completed in December - 598 m3 of reinforced concrete structures of the building frame.