Construction progress for December 2025
05.01.2026
Go back
Construction results of THE ONE for December 2025:
Main building:
- reinforcement and concreting of vertical structures of the 1st floor - 100%
- reinforcement and concreting of the slab of the 1st floor - 100%
- reinforcement and concreting of vertical structures of the 2nd floor - 100%
- reinforcement and concreting of the slab of the 2nd floor - 100%
- reinforcement of vertical structures of the 3rd floor - 40%
- concreting of vertical structures of the 3rd floor - 30%
- installation of prefabricated reinforced concrete stairs and platforms on the 1st floor - 100%
Left podium:
- concreting of vertical structures of the -2nd floor - 100%
Right podium:
- reinforcement and concreting of vertical structures of the -1st floor - 55%
- formwork of the slab of the -1st floor - 50%
Completed in December - 598 m3 of reinforced concrete structures of the building frame.