Construction progress for October 2025
05.11.2025
Go back
Construction results of THE ONE for October 2025:
Main building:
- reinforcement of vertical structures -3rd floor – 100%
- concreting of vertical structures -3rd floor – 100%
- reinforcement of slab -3rd floor – 100%
- concreting of slab -3rd floor – 100%
- reinforcement of vertical structures -2nd floor – 100%
- concreting of vertical structures -2nd floor – 90%
- installation of bentonite mats on vertical surface -2nd floor – 100%
- installation of hydrofoil on cold joints -2nd floor – 100%
- reinforcement of vertical structures 1st floor – 50%
- concreting of vertical structures 1st floor – 50%
- reinforcement of slab 1st floor – 50%
- concreting of slab 1st floor – 50%
- installation of precast reinforced concrete stairs and platforms on -6th floor – 100%
- installation of precast reinforced concrete stairs and platforms on -5th floor – 100%
Left stylobate:
- reinforcement of vertical structures -3rd floor – 100%
- concreting of vertical structures -3rd floor – 100% installation of bentonite mats on vertical surface -3rd floor – 100%
- installation of hydrofoil on cold joints -3rd floor – 100%
Completed in October – 410 m3 of reinforced concrete building frame structures.