Construction progress for October 2025

05.11.2025

Go back

Construction results of THE ONE for October 2025:

Main building:

  • reinforcement of vertical structures -3rd floor – 100%
  • concreting of vertical structures -3rd floor – 100%
  • reinforcement of slab -3rd floor – 100%
  • concreting of slab -3rd floor – 100%
  • reinforcement of vertical structures -2nd floor – 100%
  • concreting of vertical structures -2nd floor – 90%
  • installation of bentonite mats on vertical surface -2nd floor – 100%
  • installation of hydrofoil on cold joints -2nd floor – 100%
  • reinforcement of vertical structures 1st floor – 50%
  • concreting of vertical structures 1st floor – 50%
  • reinforcement of slab 1st floor – 50%
  • concreting of slab 1st floor – 50%
  • installation of precast reinforced concrete stairs and platforms on -6th floor – 100%
  • installation of precast reinforced concrete stairs and platforms on -5th floor – 100%

Left stylobate:

  • reinforcement of vertical structures -3rd floor – 100%
  • concreting of vertical structures -3rd floor – 100% installation of bentonite mats on vertical surface -3rd floor – 100%
  • installation of hydrofoil on cold joints -3rd floor – 100%

Completed in October – 410 m3 of reinforced concrete building frame structures.