Construction Progress for January 2025
10.02.2025
Go back
THE ONE Construction Results for January 2025:
Lower left part of the stylobate:
- Reinforcement of the slab of the -3rd floor – 100%
- Concrete pouring of the slab of the -3rd floor – 100%
- Reinforcement of vertical elements of the -2nd floor – 100%
- Formwork installation for the slab of the -2nd floor – 100%
- Reinforcement of vertical elements of the -2nd floor – 100%
- Concrete pouring of vertical elements of the -2nd floor – 100%
- Formwork installation for the slab of the -2nd floor – 100%
- Reinforcement of the slab of the -2nd floor – 100%
- Concrete pouring of the slab of the -2nd floor – 100%
- Reinforcement of vertical elements of the -1st floor – 100%
- Concrete pouring of vertical elements of the -1st floor – 100%
- Formwork installation for the slab of the -1st floor – 100%
- Reinforcement of the slab of the -1st floor – 100%
- Concrete pouring of the slab of the -1st floor – 100%
- Reinforcement of the parapet vertical elements of the 1st floor – 70%
- Manufacturing of metal braces for sheet piling reinforcement – 100%
Upper left part of the stylobate:
- Excavation: 600 m³
- Retaining wall installation – 88%
Upper part of the right stylobate:
- Installation of bentonite mats on the vertical surface
- Installation of water stop on cold joints
- Concrete pouring of vertical elements of the -6th floor – 100%
- Formwork installation for the slab of the -6th floor – 100%
- Reinforcement of the slab of the -6th floor – 100%
- Concrete pouring of the slab of the -6th floor – 100%
- Dismantling of the reinforcement beam of the sheet piling – 100%
- Concrete pouring of vertical elements of the -5th floor – 80%
- Manufacturing of the reinforcement beam for sheet piling – 80%
- Pile installation for the high-rise section – 31 units
- Concrete poured – 674.5 m³