Construction Progress for January 2025

10.02.2025

Go back

THE ONE Construction Results for January 2025:

Lower left part of the stylobate:

  • Reinforcement of the slab of the -3rd floor – 100%
  • Concrete pouring of the slab of the -3rd floor – 100%
  • Reinforcement of vertical elements of the -2nd floor – 100%
  • Formwork installation for the slab of the -2nd floor – 100%
  • Reinforcement of vertical elements of the -2nd floor – 100%
  • Concrete pouring of vertical elements of the -2nd floor – 100%
  • Formwork installation for the slab of the -2nd floor – 100%
  • Reinforcement of the slab of the -2nd floor – 100%
  • Concrete pouring of the slab of the -2nd floor – 100%
  • Reinforcement of vertical elements of the -1st floor – 100%
  • Concrete pouring of vertical elements of the -1st floor – 100%
  • Formwork installation for the slab of the -1st floor – 100%
  • Reinforcement of the slab of the -1st floor – 100%
  • Concrete pouring of the slab of the -1st floor – 100%
  • Reinforcement of the parapet vertical elements of the 1st floor – 70%
  • Manufacturing of metal braces for sheet piling reinforcement – 100%

Upper left part of the stylobate:

  • Excavation: 600 m³
  • Retaining wall installation – 88%

Upper part of the right stylobate:

  • Installation of bentonite mats on the vertical surface
  • Installation of water stop on cold joints
  • Concrete pouring of vertical elements of the -6th floor – 100%
  • Formwork installation for the slab of the -6th floor – 100%
  • Reinforcement of the slab of the -6th floor – 100%
  • Concrete pouring of the slab of the -6th floor – 100%
  • Dismantling of the reinforcement beam of the sheet piling – 100%
  • Concrete pouring of vertical elements of the -5th floor – 80%
  • Manufacturing of the reinforcement beam for sheet piling – 80%
  • Pile installation for the high-rise section – 31 units
  • Concrete poured – 674.5 m³