THE ONE
Construction progress for March 2025

04.04.2025

Go back

Construction results of THE ONE for March 2025:

Lower left part of the stylobate:

  • reinforcement of vertical elements of the parapet of the -1st floor - 100%
  • parapet concreting of the -1st floor - 100%
  • reinforcement of the pool on the 1st floor - 100%
  • pool concreting - 100%
  • reinforcement of vertical elements of the 1st floor - 100%

Upper left part of the stylobate:

  • installation of bentonite mats on the horizontal surface - 100%
  • installation of hydro insulation on cold joints - 100%
  • foundation reinforcement - 100%
  • foundation concreting - 100%
  • reinforcement of vertical structures of the 6th floor - 100%
  • concreting of vertical structures of the 6th floor - 100%
  • formwork arrangement of the slab on the 6th floor - 100%
  • reinforcement of the slab on the 6th floor - 100%
  • concreting of the slab on the 6th floor - 100%
  • reinforcement of vertical structures of the 5th floor - 60%
  • concreting of vertical structures of the 5th floor - 60%
  • installation of bentonite mats on the vertical surface of the 6th floor - 100%
  • installation of hydro insulation on cold joints - 100%
  • dismantling of the beam of the shoring wall reinforcement at 163.7 - 40%

Upper part of the right stylobate:

  • dismantling of the beam of the buttress reinforcement - 100%
  • formwork arrangement of the slab on the 4th floor - 100%
  • reinforcement of the slab on the 4th floor - 100%
  • concreting of the slab on the 4th floor - 100%
  • reinforcement of vertical elements of the 3rd floor - 50%
  • concreting of vertical elements of the 3rd floor - 50%

Main building:

  • excavation of soil - 1500 m3
  • installation of sheet piling - 100%
  • concrete poured in March - 356.9 m3