Construction progress for March 2025
04.04.2025
Go back
Construction results of THE ONE for March 2025:
Lower left part of the stylobate:
- reinforcement of vertical elements of the parapet of the -1st floor - 100%
- parapet concreting of the -1st floor - 100%
- reinforcement of the pool on the 1st floor - 100%
- pool concreting - 100%
- reinforcement of vertical elements of the 1st floor - 100%
Upper left part of the stylobate:
- installation of bentonite mats on the horizontal surface - 100%
- installation of hydro insulation on cold joints - 100%
- foundation reinforcement - 100%
- foundation concreting - 100%
- reinforcement of vertical structures of the 6th floor - 100%
- concreting of vertical structures of the 6th floor - 100%
- formwork arrangement of the slab on the 6th floor - 100%
- reinforcement of the slab on the 6th floor - 100%
- concreting of the slab on the 6th floor - 100%
- reinforcement of vertical structures of the 5th floor - 60%
- concreting of vertical structures of the 5th floor - 60%
- installation of bentonite mats on the vertical surface of the 6th floor - 100%
- installation of hydro insulation on cold joints - 100%
- dismantling of the beam of the shoring wall reinforcement at 163.7 - 40%
Upper part of the right stylobate:
- dismantling of the beam of the buttress reinforcement - 100%
- formwork arrangement of the slab on the 4th floor - 100%
- reinforcement of the slab on the 4th floor - 100%
- concreting of the slab on the 4th floor - 100%
- reinforcement of vertical elements of the 3rd floor - 50%
- concreting of vertical elements of the 3rd floor - 50%
Main building:
- excavation of soil - 1500 m3
- installation of sheet piling - 100%
- concrete poured in March - 356.9 m3