support icon
2025
THE ONE
Construction progress for August 2025

03.09.2025

Go back

Construction results of THE ONE for August 2025:

Main building:

  • Reinforcement of vertical structures -4th floor - 100%
  • Pouring concrete for vertical structures -4th floor - 100%
  • Installation of bentonite mats on the vertical surface -4th floor - 100%
  • Installation of hydro insulation on cold joints -4th floor - 100%
  • Reinforcement of floor slab -4th floor - 100%
  • Pouring concrete for floor slab -4th floor - 100%
  • Reinforcement of vertical structures -3rd floor - 70%
  • Pouring concrete for vertical structures -3rd floor - 70% Reinforcement of floor slab -3rd floor - 70%
  • Pouring concrete for floor slab -3rd floor - 70%
  • Reinforcement of vertical structures -2nd floor - 20%
  • Pouring concrete for vertical structures -2nd floor - 10%

Completed in August - 528 m3 of reinforced concrete building frame structures.