Construction progress for August 2025
03.09.2025
Go back
Construction results of THE ONE for August 2025:
Main building:
- Reinforcement of vertical structures -4th floor - 100%
- Pouring concrete for vertical structures -4th floor - 100%
- Installation of bentonite mats on the vertical surface -4th floor - 100%
- Installation of hydro insulation on cold joints -4th floor - 100%
- Reinforcement of floor slab -4th floor - 100%
- Pouring concrete for floor slab -4th floor - 100%
- Reinforcement of vertical structures -3rd floor - 70%
- Pouring concrete for vertical structures -3rd floor - 70% Reinforcement of floor slab -3rd floor - 70%
- Pouring concrete for floor slab -3rd floor - 70%
- Reinforcement of vertical structures -2nd floor - 20%
- Pouring concrete for vertical structures -2nd floor - 10%
Completed in August - 528 m3 of reinforced concrete building frame structures.