Construction progress for April 2025
02.05.2025
Go back
Construction results of THE ONE for April 2025:
Upper left part of the stylobate:
- fencing arrangement - 100%
- reinforcement of vertical structures -5th floor - 100%
- concreting of vertical structures -5th floor - 100%
- reinforcement of slab on the 5th floor - 100%
- concreting of slab on the 5th floor - 100%
- reinforcement of vertical structures -4th floor - 100%
- concreting of vertical structures -4th floor - 100%
- installation of bentonite mats on the vertical surface of the 5th floor - 100%
- installation of bentonite mats on the vertical surface of the 4th floor - 100%
- installation of hydrosealant on cold joints - 100%
Upper part of the right stylobate:
- installation of bentonite mats on the vertical surface - 100%
- installation of hydrosealant on cold joints - 100%
- reinforcement of vertical elements -3rd floor - 100%
- concreting of vertical elements -3rd floor - 100%
Main building:
- excavation of soil - 4500 m3
- fencing arrangement - 100%
- pile driving - 165 pcs.
- arrangement of concrete preparation under the foundation - 80%
- installation of bentonite mats on the horizontal surface - 50%
- installation of hydrosealant on cold joints - 50%
- installation of bentonite mats on the vertical surface - 50%
- reinforcement of foundation slab - 30%
- construction of sheet pile fencing of pit - 70%
- concrete poured for the April month - 252.7 m3
