Construction progress for April 2025

02.05.2025

Go back

Construction results of THE ONE for April 2025:

Upper left part of the stylobate:

  • fencing arrangement - 100%
  • reinforcement of vertical structures -5th floor - 100%
  • concreting of vertical structures -5th floor - 100%
  • reinforcement of slab on the 5th floor - 100%
  • concreting of slab on the 5th floor - 100%
  • reinforcement of vertical structures -4th floor - 100%
  • concreting of vertical structures -4th floor - 100%
  • installation of bentonite mats on the vertical surface of the 5th floor - 100%
  • installation of bentonite mats on the vertical surface of the 4th floor - 100%
  • installation of hydrosealant on cold joints - 100%

Upper part of the right stylobate:

  • installation of bentonite mats on the vertical surface - 100%
  • installation of hydrosealant on cold joints - 100%
  • reinforcement of vertical elements -3rd floor - 100%
  • concreting of vertical elements -3rd floor - 100%

Main building:

  • excavation of soil - 4500 m3
  • fencing arrangement - 100%
  • pile driving - 165 pcs.
  • arrangement of concrete preparation under the foundation - 80%
  • installation of bentonite mats on the horizontal surface - 50%
  • installation of hydrosealant on cold joints - 50%
  • installation of bentonite mats on the vertical surface - 50%
  • reinforcement of foundation slab - 30%
  • construction of sheet pile fencing of pit - 70%
  • concrete poured for the April month - 252.7 m3